Watsonville's largest park has spent about two and a half years behind chain-link. On Sunday, November 22, the City's Parks and Community Services Department plans to take that fencing down at 1301 Main St. The Ramsay Park that opens will have new fields, a new dog park and a new playground. The Santa Cruz Sentinel also reports that it keeps elements of the park generations of local families already know.
It is also a park whose final shape was set in large part by things a visitor will never see. A PG&E gas transmission line runs underneath it. The Watsonville Nature Center was planned for the south side of the park and was later moved into the Ramsay Family Center. Those two facts explain why the project took longer than first scheduled, why a new walkway appears where none was originally drawn, and why the reopening on the 22nd covers the outdoor park while the wetlands center follows in 2027.
The afternoon of November 22
The City has planned the reopening as a full afternoon. According to the Sentinel's October 21 report, recognitions are staggered across the park, so arriving later still catches part of the program:
- 1 p.m. Ribbon cutting and grand reopening
- 2 p.m. Recognition of the new dog park
- 2:45 p.m. Recognition of the Gulermovich Multi-Use Field
- 3:30 p.m. Recognition of the Sotomayor Soccer Field and its accompanying art feature
A "Rediscover Ramsay" scavenger hunt runs through the day. It suits an afternoon whose whole purpose is learning a familiar park's new layout.
A 1973 park, rebuilt around what people already used
Ramsay Park was first built in 1973. It is named for Will Ramsay, a former mayor and longtime local veterinarian. The park changed in pieces over the decades. In 1991 it gained new playgrounds, ball fields, an amphitheater and tennis courts. A skate park followed in 2016 and a pump track in 2021. The City began looking at a full makeover after its draft Park Master Plan was completed in 2019.
The Watsonville City Council approved a construction contract with Robert A. Bothman in 2024, and a groundbreaking followed that May. Funding came from Measure R, the American Rescue Plan Act, and state grants from Assembly Speaker Robert Rivas. The Sentinel describes the work as a $33 million project.
Here is how the renovation lines up against the park it replaces:
| Part of the park | What it was | What the renovation brings |
|---|---|---|
| Playground | Playgrounds from the 1991 round of improvements | An inclusive playground with a sensory play area, cargo nets, and swings and see-saws that fit several children at once |
| Ball fields | Fields from 1991 | A new multiuse field for soccer and softball, plus a renovated Sotomayor Field with hillside spectator seating |
| Amphitheater | Built in 1991 | A concrete amphitheater |
| Dogs | No dedicated area listed in the park's history | A dog park with separate areas for large and small dogs |
| Nature | A small trailer that housed the Nature Center for 16 years | A new Nature Center in the renovated Ramsay Family Center, planned for Summer 2027, plus a picnic area and an accessible trail |
The pipe that set the pace
The original construction contract was $24,530,000. The City issued the notice to proceed on June 3, 2024. From almost the start, the gas line was the hardest part of the job.
A June 23, 2026 City Council agenda report lays out the history change order by change order. In December 2024 the contract grew to cover potholing around critical gas transmission lines that PG&E required. In September 2025 another change order paid for extra work with PG&E to remove a retired gas transmission line, along with a new entrance and gate at the play area. In March 2026 the parking lot design was changed because of elevation problems created by the gas line's existing concrete cap.
PG&E's rules for utility crossings often require expensive alternatives to excavation, "as heavy equipment is not allowed for work near the pipe." Crews used HydroVac excavation, which digs with pressurized water and suction, to install conduit near the gas lines. They also rerouted conduit in the parking lot so it crossed the line fewer times. City staff wrote that working around the PG&E lines "continues to represent challenges, most notably in the playground / dog park area and the parking lot."
The ground caused trouble even away from the pipe. In January 2025 the Council approved $587,708.10 to remove and replace unsuitable soil under the multiuse field and add two extra layers of engineered fabric. A year later the Council approved a 168-day time extension.
By the June report, staff were recommending a tenth change order that would bring total change orders to $3,585,564.16. That is 14.62% over the original contract. Staff also broke out the larger additions, meaning the time-extension costs, the restroom renovation and the new southern access path. Without them, they calculated that changes within the original scope came to 7.64%. At the end of May the project was 85.5% complete. New sod had just gone down on Sotomayor Field, and work was moving ahead in the playground and dog park area and the Main Street parking lot.
Why the Nature Center comes later, and what its move added
The Nature Center was first planned for the south side of the park. It now has a new home in the renovated Ramsay Family Center. Watsonville Wetlands Watch, which is building the center in partnership with the City, describes a space of about 3,000 square feet. It replaces the small trailer that served the community for 16 years. The group says the exhibit designs are complete and the project is fully funded through grants and private donations. It has put out a request for proposals to find a fabrication partner to build the exhibits ahead of a planned Summer 2027 opening.
That puts the park and its wetlands education space on two separate timelines. The November 22 reopening covers the fields, the playground, the dog park and the grounds. The indoor Nature Center comes later, in a building that already stands at the park.
The move also changed the outdoor park. With the Nature Center gone from the south side, the design had a gap. In May 2026 the Council approved Change Order No. 9 to fill it with a new accessible route from the playground and dog park area down to the lower parking lot. The route is an 8-foot-wide concrete walkway with site furnishings and six new pedestrian lights. That change order totaled $958,523.61, including two months of extended overhead. Because the Main Street lot was under renovation, the City also built a separate construction entrance off Main Street so work could continue inside the Family Center.
So the lit walkway from the playground to the lower lot is a direct result of the Nature Center's move. It was added to connect the parts of the park the Nature Center was originally meant to link.
Details to look for on a first visit
Some of the smaller changes in the June report are easy to see on the ground once the fences come down.
- Gates between the dog areas. The big-dog and small-dog areas are separate, and gates were added to the fence between them. The design also added ornamental fencing behind the adjacent picnic area and more irrigation for newly planted trees.
- Half-field lighting at Sotomayor. The MUSCO lights at the Sotomayor Soccer Field were wired with extra circuits so that half the field can be lit at a time, which was the original intent.
- A longer wall behind the softball backstop. City staff asked for the block wall behind the backstop at the multiuse field to be extended on both sides to hold back soil from the higher ground around it.
- EV chargers. An early change order paid for upgraded EV charger models.
The dog-area gates make it easier to move between the two sides and to maintain them. The half-field lighting lets one end of Sotomayor Field be lit without the other. The backstop wall is there because the ground around the multiuse field sits higher than the field.
The City keeps the project overview on its Ramsay Park Renaissance Project page. That page is the place to check for updates between now and the 22nd.
I've watched Ramsay Park change over more than three decades of working in Santa Cruz County, and I'm glad to see this reopening. If you'd like to talk through how a park like this fits into the part of Watsonville you live in or are considering, I'm happy to share what I know. Katy King is here when you're ready. Let's Connect.